The change to excavate bridge abutment #2 deeper significantly impacted the project schedule. All work was completed within the revised Contract time allotted to account for the Change.
Job Number:
133
Owner:
County of Del Norte
Owner Contact:
James Bamts
Owner Phone:
(707) 464-7229
Start Date:
Completion Date:
Contract Value:
In Progress
Project Overview:
Bridge replacement project with cast-in-place box girder bridge
Final Amount:
In Progress
Contract Number:
2017-050
Change Comments:
Owner directed bridge abutment #2 footing be excavated deeper, requiring a custom shoring box, additional excavation, and revised falsework.
Award Date:
5/11/2017
Performance Comments: