Repair Erosion Around WWTP Outfall Pipe with Rip Rap
Techn. Work Description:
Excavation of a toe trench and placement of 1660 tons 1/2 ton armor rock on backing rock to reinforce the existing waste water treatment plant outfall pipe.
Final Amount:
$126,293.00
Contract Number:
Bid No. 2010-8
Change Comments:
Increased quantity of rock to provide additional erosion protection.