Site Under Construction: Updated information will be available soon.

Reconstruction of Hyampom Road, CR 301

Project completed within the alloted time. Project suspended during the winter of 2011/2012.

Job Number:

102

Owner:

County of Trinity

Owner Contact:

DOT Randy Cessna

Owner Phone:

(530)623-1365

Start Date:

6/1/2011

Completion Date:

240 WD

Contract Value:

$3,337,276.00

Project Overview:

Reconstruction of Hyampom Road, County Road 301 Including Common & Rock Excavation, Embankment, Arch Culvert, Rip Rap, Paving

Final Amount:

$3,337,276.00

Contract Number:

11-ROAD-1

Change Comments:

Major Changes: Increase structural section thickness, rockfall protection added, drainage system modifications, and variation in quantities.

Award Date:

6/16/11

Performance Comments:

Project completed within the alloted time. Project suspended during the winter of 2011/2012.