Site Under Construction: Updated information will be available soon.

Maybert Bridge at Canyon Creek Replacement

Owner directed changes and winter suspension extended the project completion date. All work was completed in the allotted contract time.


Job Number:

125

Owner:

Nevada County, CA

Owner Contact:

Greg Ziess

Owner Phone:

916-367-8059

Start Date:

7/16/2016

Completion Date:

12/9/2016

Contract Value:

Project Overview:

Removal of an existing bridge and replacing it with an 80 foot long single-span manufactured structural steel bridge.



Final Amount:

Contract Number:

224017

Change Comments:

Award Date:

Performance Comments:

Owner directed changes and winter suspension extended the project completion date. All work was completed in the allotted contract time.