Echo Summit Rock Fall Protection

Timber clearing permit delays pushed the project start date to September. Inclement weather ended up pushing project into winter suspension. Work completed Spring/Summer 2010 after snow melt.

Job Number:

93

Owner:

State of California Department of Transportation

Owner Contact:

Brandon Miller

Owner Phone:

530-621-0985

Start Date:

9/1/2009

Completion Date:

45 WD

Contract Value:

$645,790.00

Techn. Description :

Cover Cut Slopes with Cable Mesh Drapery System

Techn. Work Description:

Covered three (3) different cut slopes with a colored pvc coated cable mesh drapery system (8,150 SY), including timber falling upper slope areas, and drilling and grouting cable anchors (80 EA).


Final Amount:

$645,790.00

Contract Number:

03-4E4104

Change Comments:

Variation in estimated quantities.

Award Date:

6/24/09

Performance Comments:

Timber clearing permit delays pushed the project start date to September. Inclement weather ended up pushing project into winter suspension. Work completed Spring/Summer 2010 after snow melt.

Project Manager:

Justin Babcock

Super Intendent:

Scott Feri

Major Contractors:

Niels Custom Blasting – Drilled for Cable Anchors