Work completed within allotted contract time. Time included a plant establishment period.
Job Number:
100
Owner:
State of California Department of Transportation
Owner Contact:
Anthony Granados
Owner Phone:
(530) 527-8417
Start Date:
8/23/2011
Completion Date:
290 WD
Contract Value:
$1,377,019.00
Techn. Description :
Installation of Cable Barrier System, Imported Fill, Drainage
Techn. Work Description:
Project involved changing the divided highway median grade and installation of a cable median barrier. Major items included 18,500 CY Import Borrow, 6,220 SY Vegetation Control Concrete, 14,670 LF High Tension Cable Barrier, 21 Acres Erosion Control, Microwave Video Detection System, Drainage System Modifications.
Final Amount:
$1,377,019.00
Contract Number:
02-2E2404
Change Comments:
Drainage changes, variation in estimated quantities.
Award Date:
4/25/11
Performance Comments:
Work completed within allotted contract time. Time included a plant establishment period.
Project Manager:
Justin Babcock
Super Intendent:
Fred Simpson
Major Contractors:
Apex Fence Company, Inc. – Cable Barrier, Guard Rail.
Steve Cox Construction – Vegetation Control Concrete.
Selby’s Soil/Erosion Control, Inc. – Erosion Control