Mill Creek Bridge

Project start date was deferred until the Spring high creek flows receded. Contract time was extended and all work was completed within the allotted Contract time.

Job Number:

106

Owner:

State of California Department of Transportation

Owner Contact:

Anthony Granados

Owner Phone:

(530) 527-8417

Start Date:

7/1/2013

Completion Date:

9/19/13

Contract Value:

$740,309.86

Techn. Description :

Repair Bridge Scour with Rip Rap. Place Polyester Concrete Overlay on Bridge Deck.

Techn. Work Description:

Maintenance of the Mill Creek bridge including a two stage stream diversion that maintained fish passage, dewatering, structure excavation and rock slope protection placement around bridge abutments, removal of existing asphalt concrete overlay and placement of a Polyester Concrete overlay wear surface, paving of bridge approaches and remove and replace metal beam guard railing.


Final Amount:

$740,309.86

Contract Number:

02-2C2254

Change Comments:

Variation in estimated quanities and miscellaneous extra work.

Award Date:

4/3/13

Performance Comments:

Project start date was deferred until the Spring high creek flows receded. Contract time was extended and all work was completed within the allotted Contract time.

Project Manager:

Kevin Ramstrom

Super Intendent:

Andy Jentzsch/Bill Green

Major Contractors:

Bay Line Cutting & Coring, Inc. – Polester Concrete Overlay
Apex Fence Co., Inc. – Metal Beam Guard Rail
S.T. Rhoades Construction Inc. – Paving
ABSL Construction – Remove Asphalt Concrete