Shortage of materials and inclement weather outside Contractors control delayed project. Contract time extended accordingly with all work completed within allotted Contract time.
Installation of 11,123 LF of stained galvanized wire mesh fence (installed by Subcontractor) and placement of 879 Tons of RSP to funnel wildlife into existing under highway crossing to prevent over the road crossings. Also constructed four (4) one-way wildlife “escape” ramps to allow wildlife trapt on the highway to escape while preventing entry.
Final Amount:
$433,340.47
Contract Number:
03-4E5004
Change Comments:
Variation in estimated quantities, miscellaneous extra work.
Award Date:
6/18/13
Performance Comments:
Shortage of materials and inclement weather outside Contractors control delayed project. Contract time extended accordingly with all work completed within allotted Contract time.
Project Manager:
Justin Babcock
Super Intendent:
Kelly Grisham
Major Contractors:
Frank Medina General Engineering – Fencing and Gates