Due to timing of Contract Approval, project start up deferred until Spring 2014. Project experienced two (2) winter shutdowns due to inclement weather. All work was completed in the allotted time.
Job Number:
110
Owner:
State of California Department of Transportation
Owner Contact:
Jeff Zimmerer, Resident Engineer
Owner Phone:
(707) 498-3207
Start Date:
4/15/2014
Completion Date:
10/17/2014
Contract Value:
$4,317,056.06
Techn. Description :
Curve improvement project with three (3) retaining walls including a soldier pile timber lagging wall, a soil nail wall, and a mechanically stabilized earth wall. Project design features included intregally colored cast-in-place concrete with a stacked rock texture and concrete staining of the individual patterned rocks
Techn. Work Description:
Final Amount:
$4,317,056.06
Contract Number:
02-2E3504
Change Comments:
Variations in estimated quantites, extra work performed at Force Account including slide repair.
Award Date:
7/19/13
Performance Comments:
Due to timing of Contract Approval, project start up deferred until Spring 2014. Project experienced two (2) winter shutdowns due to inclement weather. All work was completed in the allotted time.
Project Manager:
Steve Shongood
Super Intendent:
Bill Green
Major Contractors:
S.T. Rhoades Construction Inc. – Textured Concrete RW, Paving
Drill Tech Drilling & Shoring – Vertical Drilling, Soil Nails, Shotcrete
Apex Fence Co., Inc. – Metal Beam Guard Railing
Certified Coatings Company – Concrete Staining