Mendocino Pass Slope Stabilization

Assessed 7 days of liquidated damages. Delays attributed to tieback subcontractor mechanical breakdowns and weather.

Job Number:

63

Owner:

US Federal Highway Administration – FHWA – CFLHD

Owner Contact:

Orrin Lee

Owner Phone:

720-289-8797 cell

Start Date:

9/3/2003

Completion Date:

11/30/03

Contract Value:

$781,880.00

Techn. Description :

Slope stabilization, tie-back wall, horizontal drainage, road repair

Techn. Work Description:

Stabilization of a landslide using 49 EA ground anchors with anchor pads, installed on multiple benches. Access work and excavation to construct benches.


Final Amount:

$781,880.00

Contract Number:

DTFH68-03-C-00021

Change Comments:

Partnering, quantity changes, pad grouting.

Award Date:

7/9/03

Performance Comments:

Assessed 7 days of liquidated damages. Delays attributed to tieback subcontractor mechanical breakdowns and weather.

Project Manager:

Jim Wamboldt

Super Intendent:

Joe Christiansen

Major Contractors:

Avar Construction Systems, Inc. – Tieback Anchors
Jensen Drilling – Horizontal Drains