Stabilization of a landslide using 49 EA ground anchors with anchor pads, installed on multiple benches. Access work and excavation to construct benches.
Final Amount:
$781,880.00
Contract Number:
DTFH68-03-C-00021
Change Comments:
Partnering, quantity changes, pad grouting.
Award Date:
7/9/03
Performance Comments:
Assessed 7 days of liquidated damages. Delays attributed to tieback subcontractor mechanical breakdowns and weather.
Project Manager:
Jim Wamboldt
Super Intendent:
Joe Christiansen
Major Contractors:
Avar Construction Systems, Inc. – Tieback Anchors
Jensen Drilling – Horizontal Drains