Captain Jack – Olinda Tower No. 426

Work suspended for the winter 2005/2006 and redesigned. Work completed 06/08/06 – 08/03/06.

Job Number:

81

Owner:

US Department of Energy, Western Area Power Administration (WAPA)

Owner Contact:

Paul A. Hendree (N1102)

Owner Phone:

916-353-4445 or phendree@wapa.gov

Start Date:

6/6/2006

Completion Date:

60 CD

Contract Value:

$422,023.00

Techn. Description :

Erosion Mitigation at Tower No. 426

Techn. Work Description:

Designed and constructed a 3000 SF MSE wall system to stabilize the slopes surrounding the foundation for a transmission tower. Included the removal of an existing beam and plate retaining system and developing access to the tower in a steep remote location.


Final Amount:

$422,023.00

Contract Number:

DE-AC65-05WN69444

Change Comments:

Original design was not adequate due to continued erosion. We conducted a geotechnical investigation and redesigned project increasing the original scope.

Award Date:

8/12/05

Performance Comments:

Work suspended for the winter 2005/2006 and redesigned. Work completed 06/08/06 – 08/03/06.

Project Manager:

Steve Shongood

Super Intendent:

Scott Feri

Major Contractors: